Westpac Data Centre
Client: DTZ (On Behalf of Westpac)
Project Value: $2.2 Million
KEY FEATURES
- Construction of underground concrete storage chamber and diesel fuel tank reticulation system to support emergency building generators;
- Bulk excavation and removal of contaminated material;
- Site remediation including excavation and onsite treatment of petroleum impacted hydrocarbon soils;
- Decommission and removal of existing underground dilapidated diesel fuel tanks;
- Bored piles;
- Construction of hut/building facility;
- Electrical and mechanical services associated with the fuel facility upgrade works;
- Installation of new underground fuel tank infrastructure and associated appurtenances;
- Site reinstatement works including construction of new concrete and asphalt pavements.