West Connex Interchange
Client: CPB Dragados Samsung Joint Venture (CDSJV)
Project Value: $3 Million
KEY FEATURES
- Haul Road Earthworks
- Slope Stabilisation Works
- Site Remediation & Onsite Contaminated Soil Treatment Works
- All earthworks to form the tunnel access road, tunnel portal, spoil shed pad, site office and car park
- All slope stabilisation required on the rock face to the north of and immediately adjacent to the access road and tunnel portal location.
- 50,000m3 of earthworks.
- 6,300m of soil nails installed.
- 2,100m2 of shotcrete installed.
- Onsite treatment, encapsulation and partial removal of friable asbestos contaminated soils.